Front-loaded costs
The term ‘front-loaded’ refers to costs that are applied disproportionately to elements of the work that take place early on during a project or part of a project.
Suppliers may front-load costs (or prices in bids) in order to maximise their revenue early in a project by assigning overstated values to the preliminary elements of the work. For example, a contractor might front-load costs for preliminary construction work such as services diversions, demolition, setting out, groundworks, piling, and so on.
Front-loading costs can help reduce a supplier's risk on a project, by improving their cash flow and ensuring that maximum payments are received on projects that might not proceed to completion. However, making payments in excess of the value of work completed puts the client under greater financial pressure early in the project and also at greater risk if the project does not proceed, or if a supplier becomes insolvent or has to be replaced. It can also act as a disincentive for suppliers to keep to time schedules, as they may have already completed the most profitable parts of the works.
Front loading can be avoided by detailed cost planning and cash flow projection during the design development and tender stages of a project, giving the client a clear idea of how much they should be expected to pay at different stages. Tender assessment should then allow comparisons to be made between competing bids to determine whether individual tenderers have submitted excessive prices for certain aspects or stages of the works. During the construction phase, there should be careful assessment of applications for payment to ensure that the amounts paid do not exceed the value of the works completed.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February